FirstEnergy is expanding its investment and earnings-growth plans after West Virginia regulators approved a new natural-gas power plant for two of its utility subsidiaries. The company raised its 2026–2030 capital plan by $2 billion and increased its long-term core earnings growth outlook.
The approval also raises FirstEnergy’s expected need for equity or equity-like financing over the five-year period, while allowing the utilities to recover financing costs during construction through a new surcharge.
Key details
-
West Virginia approved the Maidsville Energy Center. The state’s Public Service Commission granted Monongahela Power and Potomac Edison, both FirstEnergy subsidiaries, permission to build a combined-cycle natural-gas generation facility in West Virginia.
-
The capital plan rises to $38 billion. FirstEnergy increased its 2026–2030 Energize365 investment plan from $36 billion, citing the Maidsville project.
-
Equity financing needs increase by $800 million. FirstEnergy now anticipates $2.8 billion in equity and equity-like financing over 2026–2030, up from $2 billion. The company expects to fund about 35% of the Maidsville project’s capital investment this way.
-
The company raised its earnings-growth outlook. FirstEnergy now expects long-term core earnings per share, a non-GAAP measure, to grow at a compound annual rate of 7% to 9% from 2026 through 2030. It is targeting the upper half of that range.
-
A surcharge will provide cash recovery of financing costs during construction. The approved surcharge applies while the Maidsville facility is being built.
Plain-English implications
The plan combines a larger investment program with a higher earnings-growth target, alongside a greater need for equity or equity-like capital. The surcharge provides a way to recover construction-period financing costs in cash. The announcement did not specify the project’s construction timetable or the form of the planned equity financing.