Sandur Manganese & Iron Ores Ltd plans ₹280 crore investment in its first in-mine iron ore beneficiation plant at Deogiri
- The first 3.5 MTPA unit is targeted for commissioning in August 2027; initial upgraded ore output is expected at 1.0–1.2 MTPA, with potential to reach 1.7 MTPA.
- Q2 FY27 total income rose 22% YoY to ₹1,519 crore, EBITDA increased 37% to ₹391 crore and PAT grew 88% to ₹261 crore.
- H1 FY27 total income rose 21% to ₹2,909 crore, EBITDA increased 25% to ₹749 crore and PAT grew 60% to ₹489 crore.