i-80Gold has started production mining at its Archimedes underground project in Nevada, its second underground mine to come online. Mining began on schedule, with oxide material already going to the Ruby Hill property’s heap-leach pad and sulfide material being stockpiled for later processing.
The milestone starts a staged production ramp rather than immediate full-scale output. The company plans to increase mining rates through 2027, while building out infrastructure and preparing its Lone Tree Plant to process stockpiled material.
-
Mining and development: Archimedes is on i-80Gold’s Ruby Hill property in the Battle Mountain-Eureka gold trend. The company has completed about 3,600 meters of lateral underground development. It says ground conditions remain favorable and its mining contractor is exceeding planned productivity in the upper 426 Zone.
-
Oxide ore could lift near-term leach output: Oxide material mined from the upper 426 Zone began going onto Ruby Hill’s existing heap-leach pad in mid-November. i-80Gold expects to begin recovering gold from it in the first quarter of 2027. Recent drilling found oxide mineralization outside the resource estimate used in the project’s preliminary economic assessment, and testing indicates the material can be heap-leached at lower overall cost than processing it through the Lone Tree oxide circuit. The company expects most Archimedes mineralized material mined in 2027 to be oxide, and says that could increase its heap-leach production outlook. It plans to provide full 2027 guidance early in the new year.
-
Sulfide material is being held for Lone Tree: The refractory sulfide ore from Archimedes is being stockpiled, not processed immediately. i-80Gold intends to process it at its wholly owned Lone Tree Plant, which is planned to be commissioned in the fourth quarter of 2027. The company also expects to stockpile a large portion of oxide and refractory material from its Granite Creek underground project for processing there.
-
Capital estimate rises modestly: Construction began in September 2025 and is broadly tracking the capital-development estimate in the March 2025 assessment. However, added and upgraded surface infrastructure to support future operations is expected to bring total project capital to about $57.3 million—roughly $10 million above the earlier $47.3 million estimate. Additional ventilation raises, a permanent mine dry and offices are expected to be completed during 2027.
-
Further drilling and a feasibility study are planned: Seven underground drill rigs are active, targeting about 55,000 meters across 140 holes in the lower 426 and Ruby Deeps zones. The campaign is expected to finish in the second quarter of 2027 and is intended to test extensions of the mineralized system and improve resource definition. i-80Gold plans to complete an Archimedes feasibility study in the second half of 2027.
-
Resource base and longer-term production target: As of Dec. 31, 2025, Archimedes had an indicated resource of 436,000 ounces of gold and an inferred resource of 988,000 ounces. The company says most of the current resource is in Ruby Deeps, below the 5,100-foot elevation. It is targeting combined annual gold production of 150,000 to 200,000 ounces from Archimedes and Granite Creek beginning in 2028.
The announcement puts Archimedes into active mining, but near-term gold recovery from the newly mined oxide is expected to begin in 2027, while much of the refractory material is intended for processing after Lone Tree is commissioned. The expansion also adds about $10 million to the project’s earlier capital estimate, while the planned drilling and feasibility work are intended to support the next stage of mine planning.