CaliberCos Adds $1.2 Million and Extends Canyon Village Loan Maturity

CaliberCos secured an additional $1.2 million and extended Canyon Village’s loan maturity to October 2027, funding design work for its planned 244-home conversion and a proposed federal housing loan. The move also advances plans for a second phase with 120 apartments.

CaliberCos has secured additional financing for Canyon Village, its planned office-to-housing redevelopment in north Phoenix. The project’s existing lender increased the acquisition loan by about $1.2 million, to approximately $17.7 million, and extended its maturity to October 2027.

The added capital is intended to support design work and preparation for a proposed federal housing loan, while Caliber also advances plans for a second phase of the development.

Key details

  • Loan amendment: The increase from approximately $16.5 million to $17.7 million and the maturity extension were completed November 17. Caliber did not name the lender.
  • Phase I plans: At 2512 West Dunlap Avenue, Caliber plans to convert a former office building and its parking structure into 244 homes: 150 apartments in the office space, 62 studios and 32 townhomes above the parking structure.
  • Expanded design: Caliber added just under 17,000 square feet of rentable area by redesigning the homes above the parking structure. The company plans to include that added space in its proposed Phase I federal loan rather than finance it later.
  • HUD application: Caliber is preparing a firm application for the U.S. Department of Housing and Urban Development’s Section 221(d)(4) program with BWE, a HUD-approved lender. It expects to submit the application by January 2027. The announcement does not say the application has been approved or that the HUD loan has closed.
  • Phase II: The project’s second phase, at 2510 West Dunlap Avenue, is planned to add 120 apartments. Caliber said Phase II design development drawings are complete and that it has begun advancing the phase.
  • Project background: A Caliber-sponsored investment fund and Trillium Residential acquired Canyon Village in September 2024. The site includes two former office buildings totaling about 311,706 square feet on 17.99 acres. Phoenix approved the project’s rezoning in April 2025, after granting a density variance the previous month.
  • Why Caliber is pursuing HUD financing: The proposed Section 221(d)(4) loan would have a fixed rate set before construction, a 42-year term covering about two years of construction and 40 years of amortization, and would be secured by the property without recourse to the borrower. These are features of the loan Caliber is seeking, not terms of a loan already secured.

The immediate change is additional borrowing and more time before the existing acquisition loan matures. The extra funds are designated for project design and advancement, while the longer-term HUD financing remains a planned next step rather than a completed transaction.