India Exchange Filings

Buxar Thermal Power Project Unit Dedication

SJVN Ltd says Prime Minister Narendra Modi dedicated the second 660 MW unit of its Buxar project, bringing the 1,320 MW plant to full capacity.

  • Both units are commercially operational; the second unit involved an investment of ₹7,221.09 crore.
  • The project’s total revised approved cost is ₹14,269.40 crore.
  • Designed to generate about 9,828.72 million units annually at an 85% plant load factor; 85% of power is allocated to Bihar under a long-term PPA.

Original Filing

This is an automated summary of a public document. Always check the original before relying on it.