Hindustan Zinc HZL 2.0 Growth Program Investor Presentation

Hindustan Zinc Ltd approves ₹80,000 crore HZL 2.0 program to expand metal capacity to 2.0 MTPA

  • Investment planned over 3–5 years, funded through internal accruals and debt; includes the previously approved Debari project.
  • Debari integrated zinc smelter capacity will rise to 265 KTPA within its approved budget, with commissioning expected in 2QFY29.
  • FY26 capacity utilisation was approximately 92%.