NCL Industries Ltd approves ₹595.17 crore investment in remaining 80 MW of Tuticorin renewable energy project
- The 80 MW phase completes the 130 MW project; total project cost is ₹987.17 crore.
- Funding will be through debt and internal accruals; commissioning is scheduled for February 2028.
- Board also approved unaudited standalone and consolidated Q2 and H1 FY27 results, with unmodified limited review reports.
- Odisha cement plant proposal remains preliminary, with no land allotment or binding commitment.