Dalmia Bharat Targets 75 MT by FY28 Amid Best-Ever EBITDA

May 1, 2026 9 mins read Firehose Gupta

Dalmia Bharat Limited — Q4 FY26 Earnings Call (held Apr 28, 2026)

1. Overall Tone of Management: Optimistic

  • Management highlights “best-ever EBITDA” and “ever-highest EBITDA of Rs 3,083 crores” and frames FY27/FY28 as an execution-driven growth runway.
  • Despite acknowledging headwinds (West Asia-driven cost inflation, logistics/packing), they repeatedly express confidence that price momentum can mitigate costs (“optimistic that this positive momentum on prices will continue”).
  • They also maintain conviction on expansion milestones (“first milestone… by financial year ’28… 75 million tons”) and ROCE improvement.

2. Key Themes from Management Commentary

  • Macro & demand outlook: India growth remains strong; management expects cement demand CAGR of 7%–8% in the medium term and sees infrastructure/affordable housing capex as the key tailwind.
  • Cost inflation from West Asia conflict: Industry cost pressure is concentrated in power & fuel, packing bags, and logistics; petcoke cited at ~$160/ton and rupee depreciation as additional drag.
  • Price-cost balancing: April price improvements in “most key markets” are expected to offset cost headwinds near term.
  • Profitability & cost leadership: FY26 delivered best-ever EBITDA and management claims lowest quarterly total cost per ton in last five years; they emphasize ongoing cost take-out but avoid committing to speed.
  • ROCE focus: ROCE from core cement assets improved from 9.9% to 12.1%; commissioning of CWIP should further lift returns.
  • Expansion execution: Projects (Belgaum, Pune, Kadapa) progressing; Belgaum commissioning expected ahead of schedule; Kadapa minor Q4 delays but still targeted Q2–Q3 FY28.
  • Balance sheet discipline: Net debt Rs 1,428 crores, net debt/EBITDA 0.46x, well below their 2.0x threshold.
  • Sustainability & governance: Renewable power scaling (targeting 576 MW soon); governance/contingent liabilities described as well-controlled.
  • Legal update: ED land attachment case progress—alleged proceeds reduced from Rs 793 cr to Rs 93 cr and land release via bank guarantee.

3. Q&A Analysis

Theme A: Volume growth, market share, and utilization

  • Core questions
  • Outlook for volumes and market share after recent issues (breakdowns, “continued market share loss” referenced by analyst).
  • Whether the trade share trend implies a structural shift.
  • Management response
  • Emphasized “profitable volume growth” and capacity utilization ramp-up from new lines.
  • Explained the quarter’s softness as unexpected breakdowns (East India) and March disruptions; expects recovery and outperforming industry over coming quarters.
  • On trade share: called it not a “new normal”; expects mid-60s to high-60s over time.
  • Notable/partial aspects
  • Market share question largely reframed to profitability/utilization rather than giving a clear market-share target.

Theme B: Capacity targets and capex roadmap (75 MT by FY28; beyond)

  • Core questions
  • Why the “70/110–130” chart was “missing” and what the current capacity targets are.
  • Breakdown of how the 75 MT by FY28 will be achieved (ordering stage, readiness, capex sufficiency).
  • Confidence given Kadapa timing shift (Q2→Q3 FY28) and lack of further announcements.
  • Management response
  • Reaffirmed 75 MT by FY28 as the first milestone; long-term 110–130 MT by 2031 remains.
  • Stated they are “chasing 72 to 75 million tons in the next two years by FY ’28.”
  • Kadapa: minor delays; commissioning Q2–Q3 FY28; Belgaum ahead.
  • On 75 MT “gap”: repeatedly said they can’t share details yet; will provide more with future announcements.
  • Notable/strong vs evasive
  • Evasive on specifics: analysts asked for project-by-project capex/ordering status and 75 MT “how”; management deferred (“can’t talk right now… share whenever ready” / “wait for more announcements”).
  • However, they did provide quantitative capex ranges for FY27 and cost impact ranges for Q1/Q2 (see Theme C).

Theme C: Cost inflation (West Asia), price pass-through, and near-term cost guidance

  • Core questions
  • Expected cost impact in Q1/Q2 due to petcoke/packing/logistics.
  • Whether April price hikes are sufficient to protect margins.
  • Packaging vs fuel/logistics split of expected cost increase.
  • Management response
  • Quantified near-term cost risk: “impact of somewhere between INR125 to INR150 per ton” from Q4→Q1.
  • Split guidance: packing INR80–90/ton, remainder split between logistics and power/fuel.
  • Price pass-through: claimed April cost increases have been passed through (“we’ve been able to pass on through the price increase”) and expects margin protection, but acknowledged uncertainty (“dynamic world”).
  • Notable/strong
  • This is one of the more numerically specific parts of the call (cost risk range + packaging split).

Theme D: Capex guidance and cash flow/capex vs cash outflow reconciliation

  • Core questions
  • FY27 capex total and whether it includes only ongoing projects.
  • Reconciliation of higher fixed asset changes vs lower capex outflow in FY26; whether FY27 includes FY26 liabilities.
  • Capex breakdown: expansion vs maintenance vs renewables/efficiency.
  • Management response
  • FY27 capex: Rs 3,200–3,400 crores (explicit).
  • Cash outflow reconciliation: explained that CWIP/payables and deferred cash flows caused the gap; FY27 includes payment of FY26 liabilities (“Next year’s number includes the liability of this year”).
  • Capex breakdown: roughly Rs 2,200–2,300 crores for expansion projects; rest is regular capex; avoided finer project-wise split.
  • Notable/partial
  • Provided ranges but avoided granular project-wise capex and pending cash-out percentages.

Theme E: Incentives receivable/collections and government payment delays

  • Core questions
  • Incentive run rate/booking for FY27; whether government delays are structural.
  • Trade vs non-trade mix implications for receivables.
  • Management response
  • Incentives: Q4 collections subdued due to state government payout delays on elections; expects normalization.
  • FY27 incentive booking referenced by analyst as “INR200 odd crore” and management confirmed.
  • On receivables: management said no spike and receivable days are “normal.”

Theme F: Fuel mix strategy and availability of raw materials

  • Core questions
  • Whether they expect meaningful shift away from petcoke; fuel mix quantification.
  • Any raw material availability issues (petcoke/PVC granules).
  • Freight sensitivity to diesel price.
  • Management response
  • Fuel mix: directionally moving to alternatives (washed coal/local petcoke/alternates) but no plant-level guidance due to region/plant variability.
  • Availability: disruptions overcome; no availability concern expected.
  • Freight sensitivity: ballpark 5% diesel increase ≈ Rs 15/ton cost.

Theme G: Legal/regulatory overhang

  • Core questions
  • SFIO/MCA mutual fund case reopening—any notices/progress.
  • Management response
  • Declined to comment on rumors; stated no communication received at company level.

4. Guidance / Outlook

Explicit guidance (quantitative)

  • Cement demand: 7%–8% CAGR (medium term).
  • Capacity:
  • 75 million tons by FY28 (first milestone).
  • Near-term capacity ramp: 72–75 million tons in next two years by FY28.
  • Current expansion to reach 61.5 million tons in 18–20 months; Belgaum commissioning ahead; Kadapa commissioning Q2–Q3 FY28.
  • Capex:
  • FY27 capex: Rs 3,200–3,400 crores.
  • Expansion linked cash outflow FY27 expected Rs 2,200 crores; total capex outlook Rs 3,200–3,400 crores.
  • Cost inflation (near term):
  • Q1 impact vs Q4: INR125–INR150 per ton.
  • Packaging component: INR80–90 per ton (balance split logistics + power/fuel).
  • Cost take-out (internal):
  • Target INR50–INR100 cost take-out annually (no fixed speed).
  • Expansion cash flow / capex outflow:
  • FY27 expansion linked cash outflow: ~Rs 2,200 crores.
  • Renewables:
  • Commissioning 128 MW soon; total RE capacity to 576 MW.
  • Freight sensitivity:
  • 5% diesel price increase ≈ Rs 15/ton.

Implicit signals (qualitative)

  • Price pass-through confidence: April price hikes have “passed on” cost increases; management hopes for no margin compression, but repeatedly calls out uncertainty.
  • Execution confidence: Belgaum ahead of schedule; Kadapa “back on track.”
  • No structural guidance on volumes: they aim to outperform industry but avoid giving volume numbers.
  • Fuel mix flexibility: they will mitigate petcoke inflation via sourcing/mix changes rather than assuming petcoke cools.

5. Standout Statements (directly revealing)

  • Cost headwind quantified:impact of somewhere between INR125 to INR150 per ton” (Q4→Q1).
  • Packaging split:Packing would be somewhere between INR80 to INR90.”
  • Price pass-through claim:we’ve been able to pass on through the price increase… hopefully we should be able to protect the margins.”
  • ROCE improvement:improve… from 9.9% to 12.1%” (core cement assets).
  • Capex discipline / leverage:net debt-to-EBITDA of 0.46x… well below… 2.0x.”
  • Incentive collections issue attributed to elections: collections “subdued… due to delays in pay-outs by a few state governments on account of elections.”
  • Legal progress: ED attachment reduced from “INR793 crores to INR93 crores” and land release via bank guarantee.
  • Trade share not structural:This is definitely not the new normal… mid-60s to high-60s” (steady-state aspiration).

6. Red Flags / Positive Signals

Red flags
Guidance gaps / deferrals: repeated refusal to provide project-by-project capex, ordering status, or detailed breakdown of how the 75 MT gap is closed (“can’t talk right now” / “wait for more announcements”).
Margin protection depends on price behavior: management is optimistic but acknowledges “dynamic world” and uncertainty on energy/supply chain.
Incentive receivables volatility: collections subdued due to government election-related delays; while management expects normalization, it remains a working-capital risk.
Utilization/CC ratio trend acknowledged: CC ratio discussed as declining (analyst noted 1.7→1.6); management said it’s dynamic and medium-term improvement only.

Positive signals
Numerical near-term cost guidance (INR125–150/ton; packaging split).
Strong profitability metrics: FY26 “best-ever EBITDA” and PAT jump; Q4 cost per ton lowest in 5 years.
Balance sheet strength: net debt/EBITDA 0.46x and explicit capital allocation framework.
Execution credibility on ongoing projects: Belgaum ahead; Kadapa back on track with revised commissioning window.


7. Historical Comparison & Consistency Analysis (vs prior 3 calls provided)

a. Change in Tone Over Time

  • Current (Q4 FY26): More confident/optimistic on profitability and execution; provides clearer near-term cost numbers (INR125–150/ton).
  • Prior (Q3 FY26, Jan 21 2026): Tone was optimistic but more focused on demand momentum and “prices supportive,” with less explicit West Asia-driven cost quantification.
  • Shift classification: More Optimistic
  • Current call adds stronger performance framing (“best-ever EBITDA,” “lowest cost in 5 years”) and more concrete cost-risk ranges.
  • Still, they avoid volume guidance and keep deferring 75 MT “how,” so optimism is not fully matched by transparency.

b. Tracking Past Commitments vs Outcomes

  • Cost take-out journey: In Q3 FY26, they guided structurally toward cost take-out and referenced “INR150–200 per ton” earlier journey. In Q4 FY26 they state: “internally… INR50 to INR100 cost take-out on an annual basis” and show cost per ton improvements since Q1 FY25.
  • Assessment:Delivered / on track (they cite Q4 lowest cost in 5 years and adjusted cost decline).
  • Expansion commissioning timelines (Belgaum/Kadapa):
  • Q3 FY26: Belgaum/Pune and Kadapa “progressing as per schedule.”
  • Q4 FY26: Belgaum ahead; Kadapa had minor delays but still targeted Q2–Q3 FY28.
  • Assessment:Mostly delivered, ⏳ Kadapa slightly delayed.
  • 75 MT by FY28 roadmap:
  • Q3 FY26 and earlier: target reiterated; Jaisalmer decision/JP outcome referenced.
  • Q4 FY26: target reiterated but analysts still pressed on “gap” and ordering stage; management continues to defer details.
  • Assessment:Delayed transparency / execution still pending (no concrete “gap closure” explanation yet).

c. Narrative Shifts

  • Cost narrative changed materially: earlier calls emphasized GST-driven dynamics and relatively stable costs; now management explicitly attributes cost pressure to West Asia conflict with petcoke at ~$160/ton and quantifies cost impact.
  • Demand narrative remains steady (7–8% CAGR), but near-term demand/price uncertainty is more pronounced due to cost shocks.
  • Trade mix narrative: earlier quarters discussed trade share around low-60s; now management more explicitly frames trade share as temporary and sets a medium-term path (mid-60s to high-60s).

d. Consistency & Credibility Signals

  • Credibility: Medium-High
  • Strength: consistent emphasis on ROCE, cost leadership, balance sheet discipline; provides quantitative cost guidance for near term.
  • Weakness: recurring deferrals on project-level details and how 75 MT gap is funded/ordered; relies on “wait for announcements” rather than giving verifiable milestones.

e. Evolution of Key Themes

  • Demand: Stable bullish stance (7–8% CAGR) across calls.
  • Margins/costs: Deterioration risk increased in Q4 due to West Asia; management counters with price pass-through claims and cost mitigation.
  • Expansion: Execution remains central; minor timing adjustments (Kadapa) but overall roadmap intact.
  • Working capital/incentives: Incentive collections volatility tied to government actions becomes more explicit in Q4.

f. Additional Insights (cross-period intelligence)

  • The company is increasingly using “internal mitigation + price pass-through” as the core defense against external shocks (petcoke/logistics), rather than assuming external costs will normalize.
  • Despite strong FY26 profitability, management’s lack of granular disclosure on the 75 MT “gap” suggests either (a) reliance on future announcements/optionality, or (b) uncertainty in incremental capacity additions—both reduce confidence in the exact path even if the destination remains unchanged.